Activities

WP 1 Analysis of water resources management in the Western Balkan region - Preparation
Activity
No
Title Start
date
End
date
Status
1.1 Identification of WB regional issues related to WRM 15-11-2018 14-04-2019 completed
1.2 Analyse of EU innovations in water policy and EU recommendations and legislation in water sector 15-11-2018 14-04-2019 completed
1.3 Analyse of existing curricula related to WRM in both EU and WB partner countries    15-11-2018 15-05-2019 completed
1.4 Identification of needed laboratory resources in WB HEIs and alignment with formed EU HEIs WRM laboratory equipment list 15-11-2018 14-03-2019 completed
1.5 Workshop on innovative practices in the EU water sector: barriers and opportunities 15-03-2019 14-06-2019 completed


WP 2 Development of competence-based curricula aligned with EU trends - Development
Activity
No
Title Start
date
End
date
Status
2.1 Development of specific competencies and learning outcomes of curricula in WB 15-04-2019 14-10-2019 completed
2.2 Development of courses content and syllabi 15-05-2019 14-01-2020 completed
2.3 Innovation of existing and development of new master curricula for WRM in WB 15-05-2019 14-01-2020 completed
2.4 Accreditation of master curricula 15-12-2019 14-09-2020 completed
2.5 Theme-based training of teaching staff for acquiring new teaching and learning methods 15-05-2019 14-03-2020 completed
2.6 Purchasing of literature, software and laboratory equipment, installation and activation 15-01-2019 14-11-2019 completed


WP 3 Development of trainings for professionals in water sector - Development
Activity
No
Title Start
date
End
date
Status
3.1 Introduction with LLL courses for professionals in water sector in EU 15-12-2018 14-05-2019 completed
3.2 Analyse of water sector needs for LLL courses in WB 15-12-2018 14-06-2019 completed
3.3 Development of trainings’ content and corresponding educational material 15-07-2019 14-03-2020 completed


WP 4 Implementation of developed master curricula and trainings - Development
Activity
No
Title Start
date
End
date
Status
4.1 Implementation of developed master curricula 15-10-2020 14-05-2022 completed
4.2 Implementation of trainings for professionals in water sector 15-11-2020 14-02-2021 completed
4.3 Self-evaluation of master curricula 15-01-2021 14-05-2022 completed
4.4 Self-evaluation of trainings for professionals in water sector 15-12-2020 14-03-2021 completed


WP 5 Quality assurance and monitoring – Quality plan
Activity
No
Title Start
date
End
date
Status
5.1 Development of the Quality and Assurance Plan 15-12-2018 14-04-2019 completed
5.2 Regular Quality Assurance Committee meetings 15-03-2019 14-10-2021 completed
5.3 External evaluation of the project 15-03-2020 14-06-2020 completed
5.4 External financial control 15-03-2020 14-11-2021 completed
5.5 Inter-project coaching 15-02-2020 14-05-2020 completed


WP 6 Dissemination and exploitation – Dissemination & exploitation
Activity
No
Title Start
date
End
date
Status
6.1 Creation of the Dissemination & Exploitation Plan 15-12-2018 14-04-2019 completed
6.2 Development of project website and promotional materials 15-12-2018 14-11-2021 completed
6.3 Info days for student enrolment 15-11-2019 14-10-2020 completed
6.4 Roundtables with non-academic sector 15-02-2020 14-11-2020 completed
6.5 Winter/summer schools 15-01-2021 14-05-2022 completed
6.6 Symposium for promoting WRM in WB 15-05-2021 14-08-2021 completed


WP 7 Project management
Activity
No
Title Start
date
End
date
Status
7.1 Kick-off meeting 15-11-2018 14-02-2019 completed
7.2 Brussels kick-off meeting 15-01-2019 14-02-2019 completed
7.3 Development of the Project management guide 15-12-2018 14-04-2019 completed
7.4 Regular Steering Committee & Project Management meetings 15-03-2019 14-10-2021 comleted
7.5 Day-to-day coordination of project activities 15-11-2018 14-05-2022 completed
7.6 Submission of interim and final reports 15-01-2020 14-05-2022 completed